In California, mechanic's liens must be recorded within the earlier of: (1) 90 days from when the entire project is completed or abandoned; or (2) 60 days from when a Notice of Completion or Notice of Abandonment / Cessation is filed. The filing fee to record your lien will be between $20 - $50. read more
A mechanic's lien has specific deadlines that are tied to completion dates. If you cannot finish the work, consider filing a stop notice before or instead of a mechanic's lien. Serve a California 20-day preliminary notice (view the form in the resources section). read more
3 Basic Steps - Learn How To File A Mechanic's Lien In California - Written by Attorney David J. Barnier & Diane Dennis-Dennis read more